Case Study

Packaging line cycle time reduced by 28%

Industrial automation and mechanical retrofit for a food manufacturer in Turkey.

Challenge

  • Legacy packaging line bottlenecks without replacing the entire plant.

Solution

  • Mechanical transfer redesign, PLC logic upgrade, HMI alarms for faster response.

Result

  • -28% cycle time, -35% unplanned stops, 4-week rollout.

Contact WAARDCO at [email protected] or +90 552 561 8865.